WARNING: You're looking at a page from the old site. We have relaunched with live stimulus data. Learn more here.


Recent News

Advanced search added: keywords, zip codes, and recipients 11/25/2009

Thanks to the tireless work of developer Peter Snyder, Stimulus Watch 2.0 now has an advanced search capability that will…

Jerry Brito on Washington DC’s Federal News Radio... 11/24/2009

Jerry Brito on Washington DC’s Federal News Radio discussing the new features available on Stimulus Watch 2.0.

We've relaunched with new official data of stimulus projects in your neighborhood! 11/18/2009

Welcome to Stimulus Watch 2.0. While our original site featured proposed stimulus projects taken from the U.S. Conference of Mayors…

OpenRegs.com
Find government regulations by issue or agency. Comment, add links and subscribe to regulations.

Projects in Spokane, Washington

Below are the "shovel-ready" projects for which this city submitted in the 2008 U.S. Conference of Mayors report. You can click on a project to read (and add to) its description. You can also discuss the project and vote on whether you believe it is critical or not.

The total cost of all the projects submitted by Spokane is $66,751,000

Description City State Jobs Cost Program Type Vote Ratio
Havana St Bridge; new grade separation Spokane WA 100 $18,500,000 Streets/Roads 21
Freya St Bridge; Rehabiliation project Spokane WA 100 $12,000,000 Streets/Roads 38
Maple/Walnut-Cedar-High Drive from 5th to 29th; full reconstruction Spokane WA 100 $5,500,000 Streets/Roads 24
Lincoln/Monroe from the River to 17th Ave; full reconstruction Spokane WA 100 $5,200,000 Streets/Roads 20
Perry St from SE Blvd to Arthur and Arthur from Perry to 3rd; full reconstruction Spokane WA 60 $2,700,000 Streets/Roads 13
Crestline from 37th to 53rd; full reconstruction of the roadway including new curb and sidewalk Spokane WA 60 $2,500,000 Streets/Roads 11
Barnes Rd from Phoebe to Strong Road. new roadway construction Spokane WA 60 $2,200,000 Streets/Roads 9
Mission from Hamilton to Napa (includes signal replacement at Hamilton); full reconstruction Spokane WA 40 $1,800,000 Streets/Roads 19
Wellesley fro Assembly to Driscoll; full reconstruction Spokane WA 30 $1,300,000 Streets/Roads 3
Buckeye from Post St to Division St; full reconstruction Spokane WA 30 $1,200,000 Streets/Roads -7
Garland from NW Blvd to Driscoll; full reconstruction Spokane WA 30 $1,200,000 Streets/Roads 3
5th Ave from Washington to Monroe Spokane WA 20 $1,100,000 Streets/Roads 1
5-Mile Prairie from Ash to Lincoln-Bike and pedestrian improvments; Spokane WA 20 $1,000,000 Streets/Roads 20
Fish Lake Trail; construct approx 4.4 miles of trail Spokane WA 20 $1,000,000 Streets/Roads -4
Rowan from Maple St to Wall St; full reconstruction Spokane WA 30 $1,000,000 Streets/Roads 3
Bike routes downtown-Jefferson, 4th Ave, Howard, Spokane Falls Blvd, Riverside, Main Spokane WA 20 $719,000 Streets/Roads 10
Historic Iron Bridge; rehab old RR bridge for ped and bike access Spokane WA 15 $580,000 Streets/Roads 27
Ben Burr Trail from Liberty Park to Erie/Riverside Dr Spokane WA 15 $350,000 Streets/Roads -10
Fairchild AFB Transmission Main Phase 2 Spokane WA 75 $5,876,000 Water 3
Barnes Rd Water Main Spokane WA 20 $1,026,000 Water 5