| Front Street Streetscape Enhancements (Hamilton to City Line) |
Allentown |
PA |
14 |
$11,000,000 |
Streets/Roads |
-188 |
| 7th Street Enhancements (Walnut to City Line) |
Allentown |
PA |
50 |
$7,500,000 |
Streets/Roads |
-73 |
| 8th Street Bridge Enhancements |
Allentown |
PA |
45 |
$6,000,000 |
Streets/Roads |
24 |
| Mill & Overlay 5 (five) streets: Harrison - S. Hall to S 10th; Hanover - Bridge East to Irging; Hamilton - 2nd to 5th (part of Downtown Commercial Corridor): Mack - Emaus to 8th St Underpass; and Plymouth - Union to Hanover |
Allentown |
PA |
50 |
$5,090,000 |
Streets/Roads |
-27 |
| Old Allentown Streetscape Improvements |
Allentown |
PA |
40 |
$5,000,000 |
Streets/Roads |
-47 |
| Ralumac Midway Manor & West Brook Park Neighborhoods |
Allentown |
PA |
50 |
$5,000,000 |
Streets/Roads |
-20 |
| Rehab 9 (nine) Concrete Streets: Plymouth - Union to Columbia; Arch- Parkway to Turner; 29th - Parkway to Turner; Allen - Arch to Glenwood; Walnut - 2nd to 3rd; Sherman - Union to Hanover; 4th - Washingon to Walnut; Union - 4th to 5th; and Harrison - Leh |
Allentown |
PA |
21 |
$3,565,000 |
Streets/Roads |
-6 |
| West Park Streetscape Initiative |
Allentown |
PA |
20 |
$3,000,000 |
Streets/Roads |
-25 |
| New Concrete for 6 (six) streets: Chew -23rd to 31st; Refwal - Green to Allen; Type - 14th to Mercer; Hazel - Chew to Gordon;
Page - Howard to 11th; and Monroe - 5th to Williams |
Allentown |
PA |
25 |
$2,775,000 |
Streets/Roads |
-5 |
| Hamilton Street Electrical Upgrade |
Allentown |
PA |
16 |
$2,500,000 |
Streets/Roads |
-13 |
| Traffic Calming for Chapel Ave & Parkway Blvd |
Allentown |
PA |
20 |
$2,000,000 |
Streets/Roads |
-26 |
| 19th Street Streetscape Initiative (Liberty to Tilghman) |
Allentown |
PA |
15 |
$1,500,000 |
Streets/Roads |
-2 |
| Reconstruct 1 (one) street, Union - American Parkway to RR Tracks |
Allentown |
PA |
5 |
$750,000 |
Streets/Roads |
6 |
| Ott St. Streetscape Enhancements |
Allentown |
PA |
7 |
$750,000 |
Streets/Roads |
-27 |
| Automatic Meter Reading Program |
Allentown |
PA |
60 |
$6,000,000 |
Water |
-64 |
| Ozonation Equipment for Lehigh River Intake |
Allentown |
PA |
15 |
$3,500,000 |
Water |
14 |
| Covers for Plate Settlers |
Allentown |
PA |
7 |
$1,500,000 |
Water |
-20 |
| Removal of Inflow & Infiltration |
Allentown |
PA |
15 |
$1,500,000 |
Water |
11 |
| Saintary Flow Monitoring Evaluation for Excessive Inflow & Infitlration |
Allentown |
PA |
8 |
$800,000 |
Water |
7 |
| Sewer System Extension |
Allentown |
PA |
7 |
$790,000 |
Water |
7 |
| Water Main Replacement (Contract Out) |
Allentown |
PA |
6 |
$710,000 |
Water |
24 |
| Motor Control Replacement (MCC1) – (In progress) Replacement of Major Electrical Equipment from the 1960’s that are used to run part of the Wastewater Plant |
Allentown |
PA |
3 |
$600,000 |
Water |
15 |
| Water Distribution Replacement (In House) |
Allentown |
PA |
0 |
$400,000 |
Water |
-4 |
| Centrifugally Spun Cast Iron Pipe Replacement (In House) |
Allentown |
PA |
4 |
$400,000 |
Water |
2 |
| Lehigh River Flood Dike Maintenance – Annual Maintenance on Federal Flood Control Project |
Allentown |
PA |
1 |
$250,000 |
Water |
13 |
| Miscellaneous Drainage Improvements |
Allentown |
PA |
2 |
$250,000 |
Water |
1 |
| Halstead Tank – Painting of Elevated Storage Tank |
Allentown |
PA |
0 |
$100,000 |
Water |
-7 |
| Security – Upgrades at the Wastewater Plant to meet Federal Regulations |
Allentown |
PA |
1 |
$100,000 |
Water |
11 |
| Sludge Basin Cleaning Equipment |
Allentown |
PA |
1 |
$100,000 |
Water |
-1 |
| Huckleberry Ridge Reservoir – Installation of Sodium Hypochlorite Generator for Reservoir |
Allentown |
PA |
0 |
$35,000 |
Water |
3 |
| Schantz Flooding Investigation – Evaluation of Flood Control Measures to Protect Schantz Spring |
Allentown |
PA |
0 |
$20,000 |
Water |
6 |
| City of Allentown Riverfront Development Project |
Allentown |
PA |
300 |
$20,000,000 |
CDBG |
-22 |
| City of Allentown Convention Center |
Allentown |
PA |
350 |
$20,000,000 |
CDBG |
-65 |
| General Park Improvments: Field Renovations, Drainage, Parking Lot, & Restrooms. Parks including, Cedar Beach/Parkway,Trexler & Lehigh Parkway (Wall Repairs), Keck, Fellowship East, Nice 13, East Side Reservoir, Incenerator Site, Franklin, Jordan, Jordan |
Allentown |
PA |
50 |
$6,568,000 |
CDBG |
-12 |
| City Pool Renovations (Cedar Beach, Mack, Foundtain, Jordon, & Irving) Renovations to include: New or Patching Floors, Sandblasting, Ceramic Tile, Plastering, New Filtration Systems, New Vacuuming Systems, Revised Chemical Systems, New Perimeter Piping, |
Allentown |
PA |
62 |
$5,700,000 |
CDBG |
-5 |
| Sacred Heart Neighborhood Public Improvements |
Allentown |
PA |
47 |
$5,000,000 |
CDBG |
-16 |
| Union Baptist Community Center, 6th & Chew Streets |
Allentown |
PA |
30 |
$4,000,000 |
CDBG |
-36 |
| Street Trees and Urban Forest Initiative |
Allentown |
PA |
15 |
$2,500,000 |
CDBG |
2 |
| Trail Development & Improvement: East Side- Lehigh River, Incinerator Site, Barber's Quarry Branch, Canal Park Tow Path |
Allentown |
PA |
13 |
$1,990,000 |
CDBG |
5 |
| Allentown Cemetery Improvements |
Allentown |
PA |
17 |
$1,500,000 |
CDBG |
-25 |
| Equipment for Recycling Center: Trommel Screener Tub Grinder, Trash Transfer to Trailer Compactor Unit |
Allentown |
PA |
1 |
$1,120,000 |
CDBG |
6 |
| Site Preparation & Constuction of Transer Pit for Recyling & Solid Waste |
Allentown |
PA |
6 |
$750,000 |
CDBG |
1 |
| City Hall Improvements:
Elevator Replacement,
Replacement of Lights and Trolley around City Hall Perimeter,
City Hall HVAC System |
Allentown |
PA |
5 |
$700,000 |
CDBG |
-11 |
| Bucke Boyle Bathhouse Renovation |
Allentown |
PA |
2 |
$500,000 |
CDBG |
-29 |
| Roof Replacements at various City Buildings (Ceiling at Filter Plant) |
Allentown |
PA |
5 |
$475,000 |
CDBG |
0 |
| Playground Improvements & Replacement including Safety Program |
Allentown |
PA |
3 |
$277,000 |
CDBG |
10 |
| Roosevelt/ Old Fairgrounds Improvements |
Allentown |
PA |
1 |
$200,000 |
CDBG |
-5 |