| Pilot membrane testing for a new Water Plant. |
Bozeman |
MT |
8 |
$1,200,000 |
Water |
-27 |
| Lincoln sewer main |
Bozeman |
MT |
6 |
$1,100,000 |
Water |
7 |
| Water Reclamation Plant $64 million contract to be partially (because of lack of funding) awarded November 2008 – LEED certified laboratory & administration building. |
Bozeman |
MT |
8 |
$3,177,000 |
Energy |
2 |
| Water Reclamation Plant ($64 million contract to be partially awarded November 2008) – methane recovery system/digester gas engine. |
Bozeman |
MT |
3 |
$1,000,000 |
Energy |
10 |
| Design police station and municipal court. |
Bozeman |
MT |
4 |
$2,250,000 |
Public Safety |
-113 |
| Fire engine 3 – station three is under-construction with a completion date of June 2009 |
Bozeman |
MT |
3 |
$450,000 |
Public Safety |
16 |
| Opticom system traffic preemption |
Bozeman |
MT |
2 |
$170,000 |
Public Safety |
-41 |
| Water main extension and water main replacement. replacement of ageing water tank. |
Darby |
MT |
10 |
$3,675,000 |
Water |
56 |
| wastewater lagoon to protect head waters of the Bitterroot/colombia river system |
Darby |
MT |
10 |
$5,500,000 |
Public Safety |
39 |
| Rails-to-Trails Conservancy (RTC) 2010 Campaign; provide alternative transportation; traffic and congestion mitigation; enhance air quality
? improve physical health; improve social fabric; less expense to maintain than roads; outdoor activity |
Missoula |
MT |
806 |
$50,000,000 |
Streets/Roads |
-193 |
| Higgins Streetscape, Length Of Higgins Street From Alder To Brooks Streets (complete project); general benefit; congestion mitigation; improved traffic flow; urban renewal; non-motorized traffic safety & infrastructure enhancements |
Missoula |
MT |
67 |
$4,000,000 |
Streets/Roads |
-11 |
| Hillview Way Reconstruction; safety; drainage |
Missoula |
MT |
5 |
$3,500,000 |
Streets/Roads |
3 |
| Miller Creek Road, Briggs to "Y"; safety; traffic capacity; congestion mitigation |
Missoula |
MT |
33 |
$2,000,000 |
Streets/Roads |
23 |
| Front and Main Streets, Convert to Two-Way Traffic; improved traffic flow; congestion mitigation; general benefit |
Missoula |
MT |
34 |
$2,000,000 |
Streets/Roads |
18 |
| Scott Street Overpass Reconstruction; traffic safety; maintenance |
Missoula |
MT |
31 |
$1,900,000 |
Streets/Roads |
-15 |
| North Higgins Streetscape, Phase I; general benefit; congestion mitigation; improved traffic flow; urban renewal; parking; non-motorized traffic safety and infrastructure enhancements |
Missoula |
MT |
27 |
$1,500,000 |
Streets/Roads |
8 |
| Community Sidewalks; safety, pedestrian improvements |
Missoula |
MT |
17 |
$1,000,000 |
Streets/Roads |
36 |
| Higgins/Beckwith Roundabout; urban renewal; traffic safety; congestion mitigation |
Missoula |
MT |
15 |
$900,000 |
Streets/Roads |
-24 |
| Traffic Signal Optimization; traffic operations; energy savings; congestion mitigation |
Missoula |
MT |
14 |
$800,000 |
Streets/Roads |
9 |
| Traffic Signal LED Upgrades; citywide energy efficiency; citywide fuel use reduction |
Missoula |
MT |
11 |
$600,000 |
Streets/Roads |
-1 |
| Reserve/Mullan Intersection; safety; traffic capacity; congestion mitigation |
Missoula |
MT |
6 |
$300,000 |
Streets/Roads |
18 |
| Rattlesnake Gateway Greenough; safety; pedestrian improvements |
Missoula |
MT |
4 |
$200,000 |
Streets/Roads |
-23 |
| Wastewater Treatment Plant Headworks- DEQ treatment permit requirement ? enhanced treatment process improvements |
Missoula |
MT |
108 |
$6,700,000 |
Water |
19 |
| Clark Fork Riverbank Restoration, Downtown Redevelopment. Both river banks in core downtown area, Orange to Russell Streets. Requires Corp of Engineers involvement.
(2008 failed funding process |
Missoula |
MT |
82 |
$5,000,000 |
Water |
12 |
| Wastewater Treatment Plant Odor Control ? nuisance reduction |
Missoula |
MT |
41 |
$2,500,000 |
Water |
-42 |
| Airport Sewer Interceptor system capacity, ground water protection |
Missoula |
MT |
42 |
$2,500,000 |
Water |
5 |
| Grant Creek Flood Control, Debris Removal ? flood protection |
Missoula |
MT |
17 |
$1,000,000 |
Water |
-14 |
| Storm Drain Reconstruction ? flood protection |
Missoula |
MT |
17 |
$1,000,000 |
Water |
6 |
| Sewer Liftstation Reconstruction; maintenance; ground water protection |
Missoula |
MT |
14 |
$800,000 |
Water |
11 |
| Levee Maintenance, flood protection |
Missoula |
MT |
6 |
$300,000 |
Water |
6 |
| Downtown Redevelopment and Parks, Silver Park, 14-acre inner city park with critical trail connections, public boat ramp and reconstruction of rail trestle providing access to park;inner city recreation; complete trail connections; rail/street safe |
Missoula |
MT |
77 |
$4,500,000 |
CDBG |
-2 |
| City Shops Upgrades; community services; energy efficiencies |
Missoula |
MT |
17 |
$1,000,000 |
CDBG |
-9 |
| Parks, Development, 82 acre Fort Missoula Regional Park; expand large park environment; kids, health, promote environmental stewardship; reforestation; LEED certified irrigation system; Historic interpretation; Tourism and regional area benefit |
Missoula |
MT |
341 |
$20,500,000 |
Energy |
-8 |
| Playfair Park infrastructure expansion & replacement, 60-acre park; kids, health, promote environmental stewardship; reforestation; LEED certified irrigation system; upgrade existing park environment; regional area benefit |
Missoula |
MT |
34 |
$2,000,000 |
Energy |
7 |
| Replace 15 Neighborhood Playgrounds 2009, spring; kids, health, promote environmental stewardship; improve safety for children; utilize green materials and equipment; local area benefit $100,000 each |
Missoula |
MT |
30 |
$1,500,000 |
Energy |
21 |
| Replace 3 Community Playgrounds; kids, health, promote environmental stewardship; improve safety for children; utilize green materials and equipment |
Missoula |
MT |
14 |
$600,000 |
Energy |
17 |
| City/County Facilities, Downtown Redevelopment
Downtown Police Headquarters and County Administrative Building |
Missoula |
MT |
577 |
$36,000,000 |
Public Safety |
-15 |
| Shelby Interchange |
Shelby |
MT |
20 |
$7,000,000 |
Streets/Roads |
-29 |
| Viaduct Construction |
Shelby |
MT |
20 |
$4,000,000 |
Streets/Roads |
-6 |
| City Street Paving |
Shelby |
MT |
20 |
$4,000,000 |
Streets/Roads |
2 |
| South Front Street Paving |
Shelby |
MT |
20 |
$2,000,000 |
Streets/Roads |
0 |
| Viaduct Cantilever Walkway |
Shelby |
MT |
20 |
$750,000 |
Streets/Roads |
-17 |
| Quite Zone Construction |
Shelby |
MT |
10 |
$400,000 |
Streets/Roads |
-44 |
| Sewage Treatment Expansion |
Shelby |
MT |
30 |
$6,000,000 |
Water |
9 |
| West End 12-Inch Water Line Interceptor Project |
Shelby |
MT |
30 |
$3,500,000 |
Water |
5 |
| Water Line Rehabilitation |
Shelby |
MT |
25 |
$3,000,000 |
Water |
4 |
| Water Well Field Improvements |
Shelby |
MT |
20 |
$2,500,000 |
Water |
8 |
| Wastewater Outflow Project |
Shelby |
MT |
7 |
$1,500,000 |
Water |
-1 |
| Runway Extension |
Shelby |
MT |
60 |
$15,000,000 |
Airport |
-44 |
| Amtrak Depot Improvements |
Shelby |
MT |
10 |
$200,000 |
Amtrak |
13 |
| Storm Drainage |
Shelby |
MT |
30 |
$5,000,000 |
CDBG |
-1 |
| Civic Center Energy Retrofit |
Shelby |
MT |
15 |
$1,000,000 |
CDBG |
-8 |
| Biolubricants Plant Infrastructure |
Shelby |
MT |
200 |
$10,000,000 |
Energy |
-23 |
| Rural Rental Housing Improvements |
Shelby |
MT |
15 |
$300,000 |
Housing |
-17 |
| Historic Shelby High School Distant Learning Center Development |
Shelby |
MT |
50 |
$5,000,000 |
Schools |
-12 |
| Energy Park Rail Infrastructure |
Shelby |
MT |
40 |
$4,000,000 |
Transit |
-8 |
| Transit HUB Facility |
Shelby |
MT |
6 |
$1,000,000 |
Transit |
-37 |