| W. 74th Avenue Bridge Replacement. Deficient, nonstandard bridge in need of replacement and also widening for bike and pedestrian access. |
Arvada |
CO |
0 |
$2,300,000 |
Streets/Roads |
-25 |
| W. 64th Ave. - McIntyre to Church Ditch. Completion of unfinished segment of major arterial expansion from two lanes to four lanes. |
Arvada |
CO |
0 |
$1,000,000 |
Streets/Roads |
-19 |
| Garrison Street Bridge Replacement. Replaces inadequate bridge for street, waterway, and other public improvements. Project also removes 26 homes from floodway. |
Arvada |
CO |
0 |
$1,000,000 |
Streets/Roads |
-29 |
| W. 72nd Ave. and Indiana Street (State HWY 72) Intersetion Improvements. |
Arvada |
CO |
0 |
$300,000 |
Streets/Roads |
-12 |
| Reconstruction of the highway interchange at Interstate 225, 17th Place and Colfax Ave. The project will dramatically improve access to the Fitzsimons campus ahich is home to the UCHSC Health Sciences Center. |
Aurora |
CO |
2000 |
$50,000,000 |
Streets/Roads |
14 |
| Arterial and residential reconstruction projects. ADA sidewalk and access ramp improvements. |
Boulder |
CO |
116 |
$7,500,000 |
Streets/Roads |
-91 |
| BHP, the housing authority for the city, owns and manages 337 units in eight public housing sites. Funding would go to renovate these properties, which were built between 1955 and 1982, with the majority of units built in the early 1970Â’s. |
Boulder |
CO |
65 |
$8,300,000 |
CDBG |
-159 |
| Mobile home parks in the city were built 35-50 years ago and their on-site infrastructure is deteriorating significantly. The city has funded the purchase of two parks by affordable housing non-profits and a partial infrastructure replacement |
Boulder |
CO |
30 |
$1,472,000 |
CDBG |
-139 |
| Fund installation of fire sprinklers in permanently affordable rental housing units. Nine multi-family sites, with a total of 236 unites, do not have fire protection sprinklers. |
Boulder |
CO |
10 |
$675,000 |
CDBG |
-83 |
| Provide funding to convert 60 hybrid electric vehicles to Plug-in Hyrbrid Vehicles with Vehicle to Grid technology. The cars are part of the City of Boulder, Boulder County and the University of Colorado fleets. A mix of onboard V2G technology and smart |
Boulder |
CO |
0 |
$6,000,000 |
Energy |
-954 |
| Mapleton Elementary School in the city of Boulder was built in 1889 and served as an elementary school until 2004, which it was closed due to declining enrollment. A community coalition has com together to convert the school into an early childhood educat |
Boulder |
CO |
110 |
$5,400,000 |
Schools |
-161 |
| 30th Street bikeland and sidewalk project, Broadway and Euclid transit and bike improvements, 28th Street intermodal improvements. TableMesa bike/ped underpass to park-n-ride |
Boulder |
CO |
688 |
$17,200,000 |
Transit |
-158 |
| Install a 400 bike system (40 stations) a la "Velib" in Paris, Rejuvenate HOP transit service with purchase of four new buses (US built) |
Boulder |
CO |
124 |
$3,100,000 |
Transit |
-203 |
| Install Junction Place bridge, pathways along Foothills and from Goose Creek to bus station |
Boulder |
CO |
116 |
$2,900,000 |
Transit |
-90 |
| Woodmen Corridor - Widening & Interchanges |
Colorado Springs |
CO |
100 |
$125,000,000 |
Streets/Roads |
14 |
| State Highway 21 (Powers Blvd) North, Extension to I-25 |
Colorado Springs |
CO |
200 |
$105,000,000 |
Streets/Roads |
211 |
| I-25 @ Cimarron St Interchange |
Colorado Springs |
CO |
100 |
$100,000,000 |
Streets/Roads |
-44 |
| I-25 Widening from Interquest to Northgate |
Colorado Springs |
CO |
80 |
$80,000,000 |
Streets/Roads |
31 |
| I-25 Widening from Northgate to Monument |
Colorado Springs |
CO |
75 |
$72,000,000 |
Streets/Roads |
49 |
| I-25 @ Fillmore St Interchange |
Colorado Springs |
CO |
100 |
$60,000,000 |
Streets/Roads |
28 |
| South Metro Accessibility Project (Milton E. Proby Parkway) - Academy to Powers |
Colorado Springs |
CO |
60 |
$60,000,000 |
Streets/Roads |
-50 |
| State Highway 21 (Powers Blvd) @ Airport/Stewart Interchange |
Colorado Springs |
CO |
100 |
$57,000,000 |
Streets/Roads |
-2 |
| State Highway 21 (Powers Blvd) @ Proby Parkway Interchange |
Colorado Springs |
CO |
100 |
$50,000,000 |
Streets/Roads |
-11 |
| State Highway 21 (Powers Blvd) North - Complete 3 interchanges at Briargate, Union and Old Ranch |
Colorado Springs |
CO |
100 |
$45,000,000 |
Streets/Roads |
15 |
| Local Streets Rehabilitation and Resurfacing |
Colorado Springs |
CO |
100 |
$40,000,000 |
Streets/Roads |
25 |
| I-25 Widening from Academy to Interquest |
Colorado Springs |
CO |
40 |
$37,000,000 |
Streets/Roads |
55 |
| Major Bridge Replacements |
Colorado Springs |
CO |
60 |
$30,000,000 |
Streets/Roads |
21 |
| Sidewalks and Pedestrian Ramps |
Colorado Springs |
CO |
50 |
$20,000,000 |
Streets/Roads |
-46 |
| Vincent Drive Extension - Woodmen to Nevada |
Colorado Springs |
CO |
30 |
$15,000,000 |
Streets/Roads |
-24 |
| Traffic Safety Improvements |
Colorado Springs |
CO |
25 |
$10,000,000 |
Streets/Roads |
-33 |
| Pikes Peak Highway, Erosion and Sedimentation Control project |
Colorado Springs |
CO |
30 |
$10,000,000 |
Streets/Roads |
-25 |
| Hancock Exprressway @ Chelton Road Realignment |
Colorado Springs |
CO |
15 |
$7,000,000 |
Streets/Roads |
-31 |
| Platte Avenue Widening (from Academy to Powers) |
Colorado Springs |
CO |
15 |
$6,000,000 |
Streets/Roads |
-47 |
| Centennial Drive Extension, from Fillmore to Fontanero |
Colorado Springs |
CO |
40 |
$3,000,000 |
Streets/Roads |
-30 |
| Brookside Street Reconstruction |
Colorado Springs |
CO |
15 |
$2,000,000 |
Streets/Roads |
-27 |
| Cottonwood Creek Stabilization and Detention |
Colorado Springs |
CO |
100 |
$50,000,000 |
Water |
-4 |
| Southern Delivery System - water delivery pipeline, pump station |
Colorado Springs |
CO |
45 |
$38,000,000 |
Water |
15 |
| Fountain Creek Stabilization and Enhancements, Manitou Springs to Sand Creek |
Colorado Springs |
CO |
50 |
$20,000,000 |
Water |
1 |
| Northern Nonpotable System Extension |
Colorado Springs |
CO |
35 |
$18,000,000 |
Water |
-17 |
| Southeast Nonpotable System Extension |
Colorado Springs |
CO |
30 |
$15,000,000 |
Water |
-11 |
| Local Collectors Evaluation and Replacement Program |
Colorado Springs |
CO |
30 |
$14,300,000 |
Water |
-28 |
| Sanitary Sewer Creek Crossing Program |
Colorado Springs |
CO |
25 |
$13,300,000 |
Water |
-6 |
| Water Main Replacements |
Colorado Springs |
CO |
45 |
$12,500,000 |
Water |
26 |
| Sanitary Sewer Evaluation and Rehabilitation Program |
Colorado Springs |
CO |
30 |
$10,000,000 |
Water |
7 |
| Sand Creek Regional Detention Ponds |
Colorado Springs |
CO |
25 |
$10,000,000 |
Water |
4 |
| Fountain Creek Improvements – Clear Springs Ranch for wetlands development, bank improvementsand creek realignment |
Colorado Springs |
CO |
15 |
$5,800,000 |
Water |
0 |
| Highline Reservoir Cover Replacement |
Colorado Springs |
CO |
15 |
$5,000,000 |
Water |
-6 |
| Fountain Creek Improvements – Pueblo for sediment removal and levee reinforcement |
Colorado Springs |
CO |
15 |
$4,500,000 |
Water |
8 |
| Manhole Rehabilitation and Replacement Program |
Colorado Springs |
CO |
10 |
$2,450,000 |
Water |
-10 |
| Fountain Creek Improvements – Eco-Fit Park for wetland development, drop structures and education |
Colorado Springs |
CO |
5 |
$2,300,000 |
Water |
-22 |
| Las Vegas Wastewater Treatment Plant Disinfection |
Colorado Springs |
CO |
10 |
$2,000,000 |
Water |
1 |
| Big Tooth Dam Rehabilitation |
Colorado Springs |
CO |
5 |
$1,600,000 |
Water |
10 |
| Fire Hydrant Install |
Colorado Springs |
CO |
5 |
$1,000,000 |
Water |
-25 |
| Low-Impact Development Demonstration Center to educate the public about decreasing stormwater runoff |
Colorado Springs |
CO |
2 |
$600,000 |
Water |
-100 |
| Fountain Valley Water Treatment Plant - Potable Water Mains |
Colorado Springs |
CO |
2 |
$500,000 |
Water |
2 |
| Colorado Springs Airport Business Park Interchange connecting the Defense Access Road with Airport entry/exit roads |
Colorado Springs |
CO |
100 |
$20,000,000 |
Airport |
-25 |
| Colorado Springs Airport Solar Array Project |
Colorado Springs |
CO |
50 |
$15,000,000 |
Airport |
-38 |
| Citywide Drainage Improvements |
Colorado Springs |
CO |
50 |
$20,000,000 |
CDBG |
15 |
| Area Revitalization - South Academy Blvd Infrastructure |
Colorado Springs |
CO |
25 |
$10,000,000 |
CDBG |
-22 |
| Rehabilitation/Replacement of Municipal Facilities - Fleet Maintenance |
Colorado Springs |
CO |
100 |
$6,100,000 |
CDBG |
-19 |
| Rehabilitation/Replacement of Municipal Facilities - Street Division |
Colorado Springs |
CO |
100 |
$5,605,000 |
CDBG |
-8 |
| Cottonwood Recreation Center Gym & Senior Center Expansion |
Colorado Springs |
CO |
50 |
$5,200,000 |
CDBG |
-36 |
| Area Revitalization - South Nevada Avenue Infrastructure |
Colorado Springs |
CO |
15 |
$5,000,000 |
CDBG |
-14 |
| Rehabilitation/Replacement of Municipal Facilities - Traffic Engineering |
Colorado Springs |
CO |
125 |
$4,843,000 |
CDBG |
-14 |
| 30th Street Shoulder Improvements & Bike Lanes |
Colorado Springs |
CO |
15 |
$3,050,000 |
CDBG |
-21 |
| Meter Data Management System |
Colorado Springs |
CO |
12 |
$2,000,000 |
CDBG |
-34 |
| Rehabilitation/Replacement of Municipal Facilities - Utilities Warehouse |
Colorado Springs |
CO |
75 |
$2,000,000 |
CDBG |
-20 |
| Rehabilitation/Replacement of Municipal Facilities - Parks & Recreation |
Colorado Springs |
CO |
50 |
$1,402,000 |
CDBG |
-7 |
| City Auditorium, Life Safety Improvements |
Colorado Springs |
CO |
10 |
$700,000 |
CDBG |
-29 |
| Pikes Peak Greenway Trail Paving, Dorchester Park to El Pomar Youth Sports Park |
Colorado Springs |
CO |
5 |
$495,000 |
CDBG |
-24 |
| Playground Renovations at 6 City Parks |
Colorado Springs |
CO |
10 |
$350,000 |
CDBG |
-19 |
| Sand Creek Trail Construction, Barnes Rd to Stetson Hill Blvd |
Colorado Springs |
CO |
5 |
$350,000 |
CDBG |
-27 |
| West Moreno Street Sidewalks |
Colorado Springs |
CO |
10 |
$145,000 |
CDBG |
-13 |
| Safe Routes to Schools - North Hancock Avenue |
Colorado Springs |
CO |
10 |
$118,000 |
CDBG |
7 |
| Safe Routes to Schools - Cresta Road Sidewalks & Pedestrian Ramps |
Colorado Springs |
CO |
10 |
$110,000 |
CDBG |
6 |
| Pedestrian Bridge Replacement, North Shooks Run Trail |
Colorado Springs |
CO |
0 |
$75,000 |
CDBG |
-29 |
| Research Education PV Facilities (6MW) |
Colorado Springs |
CO |
100 |
$48,000,000 |
Energy |
-64 |
| Energy Retrofits for 15 Fire Stations |
Colorado Springs |
CO |
40 |
$3,005,000 |
Energy |
-3 |
| Energy Retrofits for Other City Facilities |
Colorado Springs |
CO |
30 |
$2,000,000 |
Energy |
-5 |
| Wind Turbine for Fire Station 21 |
Colorado Springs |
CO |
5 |
$90,000 |
Energy |
-54 |
| Hancock Avenue Housing Development |
Colorado Springs |
CO |
10 |
$2,500,000 |
Housing |
-59 |
| Intermodal Transit Station |
Colorado Springs |
CO |
60 |
$12,000,000 |
Transit |
-41 |
| Purchase 16 Buses |
Colorado Springs |
CO |
0 |
$3,000,000 |
Transit |
-91 |
| Critical Stormwater Conveyance Projects: Montclair Outfall |
Denver |
CO |
112 |
$20,000,000 |
Water |
-5 |
| Critical Stormwater Conveyance Projects: Large Pipe and Manhole Rehab |
Denver |
CO |
56 |
$10,000,000 |
Water |
0 |
| Critical Stormwater Conveyance Projects: 14th and Stout Storm Drain |
Denver |
CO |
35 |
$6,200,000 |
Water |
-3 |
| Critical Stormwater Conveyance Projects: Bayaud Outfall |
Denver |
CO |
35 |
$6,200,000 |
Water |
-4 |
| Critical Stormwater Conveyance Projects: Park Hill Pond |
Denver |
CO |
31 |
$5,500,000 |
Water |
3 |
| Critical Stormwater Conveyance Projects: Cherry Creek North Outfall |
Denver |
CO |
22 |
$4,000,000 |
Water |
0 |
| Critical Stormwater Conveyance Projects: Florida Outfall Extension |
Denver |
CO |
20 |
$3,500,000 |
Water |
2 |
| Critical Stormwater Conveyance Projects: Wolff Street Bridge over Lakewood Gulch |
Denver |
CO |
8 |
$1,500,000 |
Water |
-6 |
| Operational Safety: Smart Meter parking meter replacement |
Denver |
CO |
22 |
$4,000,000 |
Public Safety |
-158 |
| Operational Safety: Safety Improvements at 15 Intersections (Signal Replacement) |
Denver |
CO |
20 |
$3,600,000 |
Public Safety |
-8 |
| Operational Safety: Upgrade Traffic Signal Control Systems |
Denver |
CO |
17 |
$3,000,000 |
Public Safety |
-2 |
| Transit Support Project: Denver Union Station
*Number of jobs created based on EPS study. This number is the annual average over years 2009-2013 |
Denver |
CO |
1190 |
$88,000,000 |
Transit |
31 |
| New Transportation Construction: Central Park Blvd Interchange |
Denver |
CO |
280 |
$50,000,000 |
Transit |
15 |
| New Transportation Construction: Broadway/I-25 Interchange Improvements |
Denver |
CO |
213 |
$38,000,000 |
Transit |
8 |
| Transit Support Project: Downtown Circulation Infrastructure |
Denver |
CO |
140 |
$25,000,000 |
Transit |
11 |
| New Transportation Construction: Federal Blvd. (7th to Holden Place) |
Denver |
CO |
115 |
$20,600,000 |
Transit |
-22 |
| Transportation Reconstruction: South Broadway (Iowa to Asbury) |
Denver |
CO |
95 |
$17,000,000 |
Transit |
-11 |