WARNING: You're looking at a page from the old site. We have relaunched with live stimulus data. Learn more here.


Recent News

Advanced search added: keywords, zip codes, and recipients 11/25/2009

Thanks to the tireless work of developer Peter Snyder, Stimulus Watch 2.0 now has an advanced search capability that will…

Jerry Brito on Washington DC’s Federal News Radio... 11/24/2009

Jerry Brito on Washington DC’s Federal News Radio discussing the new features available on Stimulus Watch 2.0.

We've relaunched with new official data of stimulus projects in your neighborhood! 11/18/2009

Welcome to Stimulus Watch 2.0. While our original site featured proposed stimulus projects taken from the U.S. Conference of Mayors…

OpenRegs.com
Find government regulations by issue or agency. Comment, add links and subscribe to regulations.

Projects in Ontario, Oregon

Below are the "shovel-ready" projects for which this city submitted in the 2008 U.S. Conference of Mayors report. You can click on a project to read (and add to) its description. You can also discuss the project and vote on whether you believe it is critical or not.

The total cost of all the projects submitted by Ontario is $17,841,100

Description City State Jobs Cost Program Type Vote Ratio
SE 5th Ave. - Bridge over I-84. Widen bridge with pedestrian/bicycle improvements. Ontario OR 480 $4,798,000 Streets/Roads -14
NW 4th Ave. roadway improvements from Tori Street to 400' West of Hwy 201. To include water and sewer upgrades. Ontario OR 140 $1,500,000 Streets/Roads 3
NW Park Blvd - Malheur Dr to NW 4th Ave. Upgrade to urban collector with pedestrian/bicycle improvements. Ontario OR 86 $862,000 Streets/Roads -6
SE 2nd St. - SE 9th Ave. to Butler Blvd. Upgrade to urban major collector with pedestrian/bicycle improvements. Ontario OR 86 $862,000 Streets/Roads -2
N. Oregon St. - N. Bypass to 1/4 north of N. Fortner St. Relocate & rebuild with pedestrian/bicycle improvements to connect with N. Bypass at NW 20th Ave. Ontario OR 85 $850,000 Streets/Roads 2
NW Park Blvd. - N Oregon St to Malheur Dr New urban collector with pedestrian/bicycle facilities. Ontario OR 70 $700,000 Streets/Roads -12
SE 5th Ave. - SE 5th St. to I-84. Upgrade to major collector with pedestrian/bicycle improvements. Ontario OR 70 $700,000 Streets/Roads -8
SW Park Blvd. - SW 11th Ave. to SW 10th Ave. New minor collector with pedestrian/bicycle improvements. Ontario OR 68 $675,000 Streets/Roads -10
SE 5th Ave. - I-84 to S. East Lane. Upgrade to urban minor arterial with pedestrian/bicycle improvements. Ontario OR 65 $650,000 Streets/Roads 1
3mg storage reservoir, booster station flow meter and SCADA, standby generator on 3,000 gpm pump, and replace check valves with pipe spools. Per 2008 Facility Planning Study. Ontario OR 254 $2,532,000 Water 7
Wastewater Improvements to include; parallel 24" FM to WWTP, Beltway pipeline, improvements near NW 8th Ave. lift station, upgrade Tapadera lift station, and relocate West Idaho lift station. Per 2008 Facilities Planning Study. Ontario OR 140 $1,394,600 Water 5
Pipelines for SW 4th and S. Dorian Dr., Washington Ave. and Yturri Beltline, Malheur Drive and Park Blvd., S. Oregon Street and 13th Ave. Per 2008 Facilities Planning Study. Ontario OR 124 $1,234,700 Water 7
Pipelines for SE 10th Street from McDaniel Mobile to SE 5th Ave., SE 2nd Ave. from SE 4th St. to SE 1st St., Northwest area improvements, and SE 5th Ave. improvements. Per 2008 Facilities Planning Study. Ontario OR 109 $1,082,800 Water 2