Total Received: $8,928,115.45 - Visit on the Web
Below you will find all the contracts, grants, and loans received by SOUZA CONSTRUCTION INC as of October 30, 2009. You can sort by the different table columns. Click on an item for more information and to comment and vote on the item.
| Type | Description | Amount | City | State | Jobs | Vote |
|---|---|---|---|---|---|---|
| Contract | Recovery Project #M109BOILM, Replace Boilers Various Facilities, Marine Corps Air Station, Miramar | $2,800,000 | San Diego | CA | 1 | 1 |
| Contract | Recovery Project # TMA-N12 Restore aged & Deteriorated Cooling Towers, Naval Medical Center, San Diego, CA | $339,118 | San Diego | CA | 0 | 0 |
| Contract | Recovery Project #PE0410 Repair Roof/HVAC 1100 Area, MCB Camp Pendleton, CA | $1,113,353 | Camp Pendleton | CA | 1 | 0 |
| Contract | Recovery Project #MI09BOILM Replace Boilers Various Facilities, Marine Corps Air Station Miramar | $2,498,891 | San Diego | CA | 1 | 1 |
| Contract | Recovery Project #RM09-1452, Facility Energy Improvements (Phase 3-HVAC), Naval Base Pt.Loma,CA | $1,063,400 | San Diego | CA | 1 | 0 |
| Contract | Recovery Project #PE0410 Repair Roof/HVAC 1100 Area, MCB Camp Pendleton, CA | $1,113,353 | Camp Pendleton | CA | 1 | 0 |