RAPID CITY,
SD
Total Received: $9,594,831.61 (sub-recipient)
- Visit on the Web
Below you will find all the contracts, grants, and loans received by Dean Kurtz Construction Company as of October 30, 2009. You can sort by the different table columns. Click on an item for more information and to comment and vote on the item.
Sub Recipient
| Type |
Description |
Amount |
City |
State |
Jobs |
Vote |
| Contract |
Rebuild shunt reactor at Ft Peck Powerplant, MT. |
$585,711 |
Rapid City |
SD |
N/A |
0 |
| Contract |
Complete design and construction of walkways between surge tanks and structural repairs to surge tank roofs at Ft Randall Dam,… |
$369,467 |
Rapid City |
SD |
N/A |
0 |
| Contract |
Complete design and construction of Lower Brule Waterline. Complete design and construction to replace Crest Road lighting feeders and fixtures.… |
$442,870 |
Rapid City |
SD |
N/A |
0 |
| Contract |
Design and construction for Tri-Lakes Office road and parking lot overlay, Littleton, CO. |
$448,849 |
Rapid City |
SD |
N/A |
0 |
| Contract |
Complete design and construction to replace Capehart Pumping Station B9529 at Ellsworth AFB, SD. |
$487,584 |
Rapid City |
SD |
N/A |
0 |
| Contract |
Complete design and construction to rehabilitate powerplant elevator and replace fire protection system at Gavins Point Dam in NE. |
$451,460 |
Rapid City |
SD |
N/A |
0 |
| Contract |
Upgrade primary electrical distribution line at Ellsworth AFB, SD. |
$736,104 |
Rapid City |
SD |
N/A |
0 |
| Contract |
Complete design and construction of asphalt overlay access road at Cottonwood Springs Dam. Complete design and construction of a new… |
$443,297 |
Rapid City |
SD |
N/A |
0 |
| Contract |
Complete design and construction of energy efficient ground source heat system |
$2,554,570 |
Rapid City |
SD |
N/A |
0 |
| Contract |
Upgrade lighting systems and controls in multiple buildings on Ellsworth AFB, SD. |
$1,553,179 |
Rapid City |
SD |
N/A |
0 |
| Contract |
Design - build a replacement paint booth in aircrafe dock on Ellsworth AFB, SD. |
$342,267 |
Rapid City |
SD |
N/A |
0 |
| Contract |
Design, realign and reconstruct approximately 2200 feet of the existing Duck Creek Road. Design and build a boat ramp at… |
$1,179,473 |
Rapid City |
SD |
N/A |
0 |