| Contract |
Contractor shall renovate bldg 2958 per scope of work date June 17, 2009. |
$1,161,089 |
Fort Knox |
KY |
4 |
0 |
| Contract |
Replace existing HVAC with Geo-thermal system in bldg 63. |
$799,740 |
Fort Knox |
KY |
0 |
-1 |
| Contract |
Switchgear Central Water Plant - Bldg.1199 |
$29,744 |
Fort Knox |
KY |
0 |
0 |
| Contract |
Renovation of bldg. 2341 (Natcher Gym) per contractor proposal dated Aug 3, 09. |
$885,113 |
Fort Knox |
KY |
3 |
0 |
| Contract |
Portable standby generator adn connection points at the west point water well fields per contractor proposal dated Sept. 3, 2009. |
$140,542 |
Fort Knox |
KY |
0 |
0 |
| Contract |
Interior renovations to bldg 1481 per contractor proposal dated July 29,2009. |
$239,751 |
Fort Knox |
KY |
4 |
0 |
| Contract |
Contractor shall replace windows in bldg. 6013 & 6014. |
$67,436 |
Fort Knox |
KY |
0 |
-1 |
| Contract |
Bldg. 298 - Renovations |
$50,595,012 |
Fort Knox |
KY |
3 |
-1 |
| Contract |
Contractor shall repair misc. gas line with locations per scope of work dated July 1, 2009. |
$813,483 |
Fort Knox |
KY |
0 |
-1 |
| Contract |
Furnish and install a 300 kw natural gas generator in Otto Gym bldg. 6591 per contractor proposal dated Sept 9,… |
$570,615 |
Fort Knox |
KY |
0 |
0 |
| Contract |
Contractor shall pull pump unit and chemically clean the well and provide acid treatment in bldgs 8033 and 8038. |
$70,400 |
Fort Knox |
KY |
0 |
0 |
| Contract |
Contractor shall remove underground storage tanks at four post sites per scope of work dated June 15, 2009. |
$31,050 |
Fort Knox |
KY |
0 |
0 |
| Contract |
Contractor shall renovate and construct an addition to the Otto Physical Fitness Center Bldg 6591. |
$1,796,701 |
Fort Knox |
KY |
6 |
1 |
| Contract |
Replace HVAC with a geo-thermal system in bldg 2341 (Natcher gym) per contractor proposal dated 7/27/09. |
$1,240,995 |
Fort Knox |
KY |
2 |
0 |
| Contract |
Install automatic transfer switch at the otter creek pumping station per contractor proposal date Sept. 3, 2009. |
$152,350 |
Fort Knox |
KY |
0 |
0 |
| Contract |
Replace existing 5 kv generator at the central water plant bldg 1199 per contractor proposal dated Sept 3, 2009. |
$466,014 |
Fort Knox |
KY |
0 |
0 |