Type Description Amount City State Jobs Vote
Contract design build of new storage barn at Steigerwald National Wildlife Refuge. Project also includes new gravel road and demo of… $156,956 Ridgefield WA 9 0
Contract Repair water control structures at the Kern County National Wildlife Refuge. $134,860 Delano CA 6 0
Contract design build of soil cover structures at the Golden Gate National Cemetery. $50,900 San Bruno CA 5 0
Contract remove and replace carpet in the administration building at the Golden Gate National Cemetery. $14,918 San Bruno CA 3 0
Contract Repair and slurry seal roads at the Golden Gate National Cemetery. $68,000 San Bruno CA 5 0
Contract design build of fish crowders at Carson National Fish Hatchery. $144,439 Carson WA 9 0