FOURFRONT KURTZ JOINT VENTURE

Primary award recipient

Type Description Amount City State Jobs Vote
Contract Rebuild shunt reactor at Ft Peck Powerplant, MT. $615,561 Rapid City SD 0 0
Contract Complete design and construction of Lower Brule Waterline. Complete design and construction to replace Crest Road lighting feeders and fixtures.… $549,748 Rapid City SD 0 0
Contract Complete design and construction to replace Capehart Pumping Station B9529 at Ellsworth AFB, SD. $619,409 Rapid City SD 0 0
Contract Upgrade primary electrical distribution line at Ellsworth AFB, SD. $867,147 Rapid City SD 0 0
Contract Complete design and construction of energy efficient ground source heat system $2,860,163 Rapid City SD 1 0
Contract Design - build a replacement paint booth in aircrafe dock on Ellsworth AFB, SD. $397,982 Rapid City SD 0 0
Contract Complete design and construction of walkways between surge tanks and structural repairs to surge tank roofs at Ft Randall Dam,… $428,148 Rapid City SD 0 0
Contract Design and construction for Tri-Lakes Office road and parking lot overlay, Littleton, CO. $472,473 Rapid City SD 0 0
Contract Complete design and construction to rehabilitate powerplant elevator and replace fire protection system at Gavins Point Dam in NE. $592,444 Rapid City SD 0 0
Contract Complete design and construction of asphalt overlay access road at Cottonwood Springs Dam. Complete design and construction of a new… $583,459 Rapid City SD 0 0
Contract Upgrade lighting systems and controls in multiple buildings on Ellsworth AFB, SD. $1,676,186 Rapid City SD 0 0
Contract Design, realign and reconstruct approximately 2200 feet of the existing Duck Creek Road. Design and build a boat ramp at… $1,217,980 Rapid City SD 0 0