Contract: $1,042,921 - Social Security Administration - Apr. 13, 2009
No votes have been cast for this award yet
Award Description: Circuit upgrades for SSA's ODAR sites.
Project Description: Service ordering commenced immediately upon receipt of order on 4/7/2009. Each of the 27 sites received their bandwidth expansions and equipment delivery and installation and those services were subsequently activated into the SSANet (Dual Carrier Network). Each site was cutover individually, with the first site cutover on 4/23/2009 and the last site completing on 6/19/2009.
Jobs Summary: Not applicable. (Total jobs reported: 0)
Project Status: Completed