Grant: $2,902,538 - Department of the Interior - Sep. 30, 2009
No votes have been cast for this award yet
Award Description: HUNTINGTON CLEVELAND SALINITY REDUCTION PROJECT - Abandon 9.1 miles of canal and eliminate winter water in 20.1 miles of canal by constructing 5.1 miles of 30 and 60 inch pipe, a new river diversion, pressure reducing stations and connecting to existing regulating ponds.
Project Description: Design engineering is approximatley 75% complete. Meetings have been held with affected agencies. Approximately 75% of required property and easements have been obtained.
Infrastructure Description: The construction will create temporary and permanent jobs
Jobs Summary: Engineering jobs created for the duration of design and construction. Constuction jobs created for the duration of construction. Agricultural water maintenance job maintained with this construction. (Total jobs reported: 4)
Project Status: Less Than 50% Completed
This award's data was last updated on Sep. 30, 2009. Help expand these official descriptions using the wiki below.
No comments have been added for this project.