Contract: $357,773 - Federal Aviation Administration - Mar. 18, 2009
No votes have been cast for this award yet
Award Description: ARTCC Elevator Replacement Design/Build Projects at ZKC, ZNY, ZME.. The projects were awarded under an existing Indefinite Delivery Indefinite Quantity contract. Provides for the Phase 1 Design, Pre-Construction and Procurement Services for the Elevator Replacement Design/Build Projects at three Air Route Traffic Control Center (ARTCC) sites as follows: Kansas City ARTCC (ZKC) at Olathe, KS; New York ARTCC (ZNY) at Ronkonkoma, NY ; and Memphis ARTCC (ZME) at Memphis, TN. Phase 1 provides for these services through the delivery of the final design and construction documents and a Change Proposal for follow-on Phase 2 construction and construction phase professional services.
Project Description: ZKC: Final Design documents have been submitted, with preconstruction services on-going including procurement, final construction proposal, and early shop drawings being obtained.ZME: Pre-final Design documents have been submitted, with Final documents to be submitted in October 2009. Preconstruction services on-going including procurement, final construction proposal, and early shop drawings being obtained.ZNY: Not yet begun
Jobs Summary: Jobs retained are primarily in architectural and engineering services to include: architecture, mechanical, electrical, fire protection and control systems personnel. Also included are project management, procurement, environmental, safety, and project control personnel (Total jobs reported: 1)
Project Status: Less Than 50% Completed
This award's data was last updated on Mar. 18, 2009. Help expand these official descriptions using the wiki below.
Funds from this award have been disbursed to subcontractors. Click here to see a list of subcontractors.