Contract: $3,998,829 - Department of the Air Force - Apr. 26, 2009
17% voted satisfied - 83% voted not satisfied - 6 vote(s) cast
Award Description: Repair North Apron Taxi Route, Phase 1
Project Description: Repair south ramp asphalt and concrete pavements and associated storm drainage system. (areas in existing T/W)
Jobs Summary: project planner, airfield escort, civil engineer, construction inspector, carpenters, laborers, equipment operator, pipelayers, supervisors (Total jobs reported: 16)
Project Status: Less Than 50% Completed
This award's data was last updated on Apr. 26, 2009. Help expand these official descriptions using the wiki below.
Funds from this award have been disbursed to subcontractors. Click here to see a list of subcontractors.
No comments have been added for this project.