IDAHO FALLS, ID

CH2M WG IDAHO LLC

Contract: $437,675,000 - Department of Energy - Apr. 13, 2009

Are you satisfied with this award? or

24% voted satisfied - 76% voted not satisfied - 17 vote(s) cast

Yes
No

Join the conversation: Post a comment about this award


Award Description: This award provides for the performance of current contractual work scope that was unfunded due to higher site funding priorities and adds new scope that includes deactivation and decommissioning of EM facilities and acceleration of the disposition of legacy materials. Specific scope items to be performed are: Deactivation & Decommissioning (D&D) • Accelerated deactivation and decommissioning (D&D) of 87 EM facilities. Remote-Handled TRU Waste Processing • Complete activities that support the processing and ultimate disposition of RH-TRU waste. Process 161 containers of RH-TRU and mixed RH-TRU waste. WAG 7 Subsurface Disposal Area (SDA) • Complete Pit 4W exhumation facility design and construction • Start Pit 4W excavation of the pit area footprint, retrieval and packaging, and shipment to WIPP of TRU and targeted waste • Complete in-situ grouting of mobile radionuclide sources as identified in the OU 7 13/14 ROD • Complete Pit 6 Targeted Waste Exhumation, Packaging, and Characterization. • Complete Pit 5 Targeted Waste Exhumation, Packaging, and Characterization. Officer Compensation Proviso: 1. A significant portion of the reported compensation is not reimbursed by the government and, in some cases, may be tied to performance factors, goals and initiatives of the corporate parents rather than the government contractor’s performance, including, at times, support for corporate goals of diversity hiring, mentoring, and participating in safety and technical reviews for other projects. 2. One individual, although he is one of the five most highly compensated officers of the contractor for reporting purposes, was not an officer of the contractor during any portion of the reporting period, FY 2008. Therefore, based on the definition of total compensation in FAR 52-204.11(a) and guidance in 17 CFR 229.402(a)(2) and (4), only total compensation from the contractor for FY 2008 is reported. 3. A significant portion of one executive's reported income represents 1) a nonreimbursible final payment under a previous incentive plan, and 2) a nonreimbursible, one-time, lump-sum mobility incentive.

Project Description: CH2M-WG Idaho, LLC on the Idaho Completion Project has performed the following activities: Deactivation & Decommissioning (D&D) • Deactivated and decommissioned 24 facilities/structures out of 87 (contract total) • Footprint reduction of 318,255 ft2 achieved out of 811,596 (contract total) WAG 7 Subsurface Disposal Area (SDA) • Buried waste retrieved 0.36 acres out of 0.91 (contract total)

Jobs Summary: Job Types Created/Retained Management 68 Technical 138 Business 21 Admin 7 Union 262 Total FTEs 496 (Total jobs reported: 496)

Project Status: Less Than 50% Completed

This award's data was last updated on Apr. 13, 2009. Help expand these official descriptions using the wiki below.


Funds Recipient

CH2M WG IDAHO LLC
IDAHO FALLS, ID 83415
See more awards to this recipient

Place of Performance

2525 N. Fremont Avenue
Idaho Falls, ID 83415
See more awards in this zip code

Funds from this award have been disbursed to subcontractors. Click here to see a list of subcontractors.




Wiki Description

No comments have been added for this project.

Edit the Wiki Description (editing policy)


Post a comment