Contract: $230,187 - Department of the Interior - Sep. 23, 2009
No votes have been cast for this award yet
Award Description: The project will rehabilitate the landscape in the vicinity of the Peirce Mill Complex and the c. 1829 Peirce Mill Structure and allow Peirce Mill to be reopened to the public. The current mill structure has structural deficiencies, is not compliant with ADA and ABA guidelines as defined in the Architectural Barriers Act Accessibility Standards, does not meet life safety codes, does not provide space comfort for users, and does not provide space comfort for users, and does not adequately represent the historic context context of the area.
Project Description: Project commenced on September 23, 2009. No activity to report.
Jobs Summary: Jobs created this quarter - 0 (Total jobs reported: 0)
Project Status: Less Than 50% Completed
This award's data was last updated on Sep. 23, 2009. Help expand these official descriptions using the wiki below.
Funds from this award have been disbursed to subcontractors. Click here to see a list of subcontractors.