Grant: $1,600,000 - Economic Development Administration - Jun. 5, 2009
No votes have been cast for this award yet
Award Description: The project is the upgrade of the existing water treatment plant in St. James Parish East Bank Water Treatment Plant in Convent, Louisiana. The project will increase the treatment capacity of the water plant from 1.5 million gallons per day to 2.7 million gallons per day.
Project Description: Contract awarded on June 22, 2009. Design work started on June 22, 2009. Expected completion date of design work is 10/01/2009. Construction bid will be advertised starting 10/22/09. Construction expected to begin 1/18/2010. Construction estimated completion 7/16/2010.
Jobs Summary: None to date (Total jobs reported: 0)
Project Status: Less Than 50% Completed
This award's data was last updated on Jun. 5, 2009. Help expand these official descriptions using the wiki below.