Contract: $1,299,566 - National Institute of Standards and Technology - Jul. 31, 2009
No votes have been cast for this award yet
Award Description: A/E services for the Project Initiation and Discovery Part II for NIST Boulder B1E Cleanroom and B1E Fit-up design
Project Description: A project assessment was substantially completed which includes the following: 1. Scientific Program Assessment including preliminary layouts with equipment/tools identified: a. A layout and process flow diagram for Options A and B (subsequently changed to read as Options C1 (9,000SF) C2 (18,000SF) and C3), b. Documented changes to the Scientific Program Assessment. 2. A review of the previously completed construction documents were reviewed to determine the changes to be made as required by the updated Scientific Program Assessment; a. A Discipline-by-discipline review of the current B1# Basic of Design Report, drawings, specifications, schedules, calculations, and product data to report any major discrepancies and deficiences and improvements. 3. Conducted three project cost assessments reflecting a project cost estimate and market condition survey. A project workshop was held at NIST on August 6 and 7 where the project assessments were presented and reviewed. The Cleanroom Fit-up Design was nitiated and achieved 95% completion on September 4. Electronic and hard copies of the Project Assessment were submitted on August 5. 50% electronic copies of the specifications and drawings were submitted on August 17. 95% electronic copies of the specifications and drawings were submitted on September 4. 100% electronic copies of the specifications and drawings were submitted on September 11 and integrated into a larger B1EB/Enhancement package for bidding. Several project and progress meetings were conducted on site at NIST Boulder and as well by 'Live Meeting.'
Jobs Summary: The ARRA funds provided to complete the NIST B1E Cleanroom B1E Fit-up design impacted the following positions: Mechanical and Structural Engineers, multiple Mechanical CADD technicians, and a Project Principal. In addtion one subcontract for over $25,000 was awarded this reporting period. (Total jobs reported: 1)
Project Status: More than 50% Completed
This award's data was last updated on Jul. 31, 2009. Help expand these official descriptions using the wiki below.
Funds from this award have been disbursed to subcontractors. Click here to see a list of subcontractors.
| Recipient | Amount | City | State |
|---|---|---|---|
| Gibbens Drake Scott, Inc. | $31,500 | KANSAS CITY | MO |