Award Description: Project to pupe the remaining .75 miles of Swalley Irrigation Main Canal; complete construction of a .75 Megawatt hydropower plant; develop/install SCADA controls and telemetry at each major lateral diverting from the Main Canal. Objectives are to stabilize water supply, improve public safety, conservation of 9,471.63 acre feet of water per season, meter water delivery and provide pressurized delivery to customers.

Project Description: Preparation to begin construction, Planning, Engineering, Contracting

Jobs Summary: 0 currently- startup is 10-19-09 (Total jobs reported: 0)

Project Status: Not Started

This award's data was last updated on Sep. 25, 2009. Help expand these official descriptions using the wiki below.


Funds Recipient

SWALLEY IRRIGATION DISTRICT
BEND, OR 97701
See more awards to this recipient

Place of Performance

Hwy 97 & MT Washington Dr
Hwy 97 & Ft Thompson Lane
Bend, OR 97701
See more awards in this zip code



Wiki Description

No comments have been added for this project.

Edit the Wiki Description (editing policy)


Post a comment