Award Description: Recommissioning/retro-commissioning of the Byron White Courthouse with the objective of reducing energy consumption to the greatest extent possible within the funding limitation. Deliverables will be a list of Energy Conservation Measures recommendation, a draft Functional Performance Testing (FPT) Plan, a Final FPT Plan and a recommissioning plan/report based on Fuctional Performance Testing. The recommissioning report will identify ECM's and their economic impact to help the GSA determine the ROI/payback period and first cost impact of the various ECM's

Project Description: Funtional Performance Testing Plan was submitted for approval. Based on the approved FPT Report, testing was conducted, A list of ECM measures was identified and submitted. A preliminary Draft Re-commissioning Report was submitted and reviewed.

Jobs Summary: HVAC Project Engineer, Electrical Project Engineer, Project Manager, Project Architect, Architectural Project Manager, Clerical (Total jobs reported: 0)

Project Status: More than 50% Completed

This award's data was last updated on Jun. 8, 2009. Help expand these official descriptions using the wiki below.


Funds Recipient

DESIGN EDGE PC
CO SPGS, CO 80903
See more awards to this recipient

Place of Performance

482 S Broadway
Suite 100
DENVER, CO 80202
See more awards in this zip code

Funds from this award have been disbursed to subcontractors. Click here to see a list of subcontractors.




Wiki Description

No comments have been added for this project.

Edit the Wiki Description (editing policy)


Post a comment