Contract: $64,000,000 - Public Buildings Service - Apr. 15, 2009
42% voted satisfied - 58% voted not satisfied - 12 vote(s) cast
Award Description: The Thurgood Marshall Courthouse infrastructure upgrade.
Project Description: During the period of May to September 30, 2009 Cauldwell Wingate Company has been working on the shop drawing coordination of the MEPS systems through out the Thurgood Marshall Courthouse. During this time the subcontractors have been ceeping detailed shop drawing, exact dimensions and location of duct work and piping above the ceiling. In the field protection of the existing historic finishes has been completed. Three floors of duct work has been fabricated and delivered to the job site with installation of two floors complete. The Electric service on three of four Con Ed serviced floors has been upgraded and electric distribution has started. Plumbing in basement for drain pipe has been installed at approximated 50% complete.
Jobs Summary: Operating Engineers Local 14, Laborers Local 79, Project Executive, Project Manager, Superintendent, Estimator, Project Accountant, Project Secretary, Sheet Metal Draftsman, Electrical Journeyman and Apprentice, Carpenter and Carpenter Apprentice, Taper, Plumber Journeyman and Apprentice, Steam fitter, Elevator person (Total jobs reported: 3)
Project Status: Less Than 50% Completed
This award's data was last updated on Apr. 15, 2009. Help expand these official descriptions using the wiki below.
Funds from this award have been disbursed to subcontractors. Click here to see a list of subcontractors.
No comments have been added for this project.