Award Description: Rehabilitation of the septic system at the Hoh Visitor Center Complex.

Project Description: Completed initial site visit; Siting analyzed and alternative D redeisgn due to relocation of drainfield by NPS staff; Coordination with DOH; Survey completed; Coordination with vendors and NPS staff; 50% design and 50% drawings underway.

Jobs Summary: Project Manager Civil Engineer CAD Technician (Total jobs reported: 1)

Project Status: More than 50% Completed

This award's data was last updated on Aug. 4, 2009. Help expand these official descriptions using the wiki below.


Funds Recipient

SVR DESIGN COMPANY
SEATTLE, WA 98101
See more awards to this recipient

Place of Performance

1205 Second Ave
Suite 200
Seattle, WA 98101
See more awards in this zip code



Wiki Description

No comments have been added for this project.

Edit the Wiki Description (editing policy)


Post a comment