Grant: $329,130 - Administration for Children and Families - Jun. 30, 2009
0% voted satisfied - 100% voted not satisfied - 1 vote(s) cast
Award Description: ARRA COLA and Quality Improvement Award
Project Description: 1.1.84% salary increases were given to 146 staff who are employed by the Head Start and Early Head Start program for the period of July-September 2009. 25% complete 2. 13 teaching staff received tuition assistance July-September 2009. 20% complete 3. 26 teacher assistants received increases in hourly compensation that moved them to $9.00 per hour for the period of July-September 2009. 20% complete 4. Renovation of the Belfast Center- 0% complete 5. Replacement of the Roof at the Chestnut Center- July-September ___ complete 6. Paying for approximately one-fourth of the cost of of a 30 passenger bus- July -September 2009- 0% complete
Project Status: Less Than 50% Completed
This award's data was last updated on Jun. 30, 2009. Help expand these official descriptions using the wiki below.