Grant: $2,858,200 - Environmental Protection Agency - Jul. 13, 2009
No votes have been cast for this award yet
Award Description: The Port Authority was awarded a national Clean Diesel Funding Assistance Program Grant in order to fund the shore power installation at the Brooklyn Cruise Terminal in Brooklyn, NY. This project will install land-side electrical infrastructure, with the general purpose of the grant being to reduce diesel emissions from the ships onboard generators and to improve the overall air quality.
Project Description: Have completed the Stage 1 design and cost estimate. Have started the Stage 3 and RFP, but have put it on hold until issues with ConEd are resolved. These issues involved the N+2 reguirement, which is redundant, as well as the issue with putting in 5 isolation transformers. These requirement from ConEd is adding an additional 6 million to the project costs. The Port Authority Plans to address these items with ConEd by arranging a meeting with upper management (Executive Director, CEO, etc) to resolve the N+2 requirement. Also planned to negotiate electrical rates with NYPA and Carnival Cruise lines.
Jobs Summary: None (Total jobs reported: 0)
Project Status: Less Than 50% Completed
This award's data was last updated on Jul. 13, 2009. Help expand these official descriptions using the wiki below.
No comments have been added for this project.